When Data Center giant Internap decided to build out a new 20,000 square foot co-location facility in Tukwila, they chose PRIME as their design-assist electrical partner. Rubicon Construction of New Jersey acted as the general contractor on this interior buildout project. Highland and Associates out of New York State was the electrical engineer of record.
The schedule for this fast track project required that the job be completed within 90 days. PRIME was up to the challenge! We managed the accelerated procurement and construction process that included crews of up to 40 electricians. PRIME led the charge in completing design, construction, commissioning and turning over of the facility to Internap on time and on budget.